Nobody wants to wait for shipping when the exam date is already circled on the calendar. Order the AD0-E911 practice questions from Prep4away and the Adobe Workfront Project Manager Certified Professional material lands in your inbox within a minute of payment, ready to download, print, and study.
Adobe AD0-E911 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Intake and Planning | 40% | - Identify different ways to be notified of a work request - Given a scenario, determine the appropriate task settings to plan the execution of a task in a specific time frame - Identify the appropriate field to view a specific assigned resource - Identify Workfront's functionality to track project risk - Given a scenario involving a persona during the intake and planning stage, identify the relevant reports and dashboards - Identify ways to locate key data on a project - Given a scenario, determine the sharing permissions that are required for an activity - Identify the correct hierarchy of objects in Workfront - Given a request, review the custom data to determine the appropriate action |
| Closeout | 10% | - Identify the project elements that can be used to measure project success - Given a particular object status, determine what activities need to be executed or what actions are triggered |
| Execute | 50% | - Identify how Workfront teams and Workfront groups can be used - Compare the differences between Condition and Progress Status - Describe team collaboration and notification features - Identify workload balancing and assignment strategies - Given a Gantt chart, explain the object relationships on the chart - Describe document proofing and approval workflows - Identify project elements related to milestones and project tracking - Identify task constraints and timelines - Identify financial tracking elements - Given a scenario involving a persona during execution, describe dashboards and reports available and how to build a custom dashboard or report |
AD0-E911 Exam Questions, Answered
Yes. A free PDF demo is available so you can review the question quality and format before you pay anything. And once you do purchase, your Adobe Workfront Project Manager Certified Professional material includes 365 days of free updates — if that update period expires, you can extend it later at a 50% discount from your member zone.
The AD0-E911 exam includes 50 questions, and you have 100 minutes to complete them. That makes pacing a real part of the challenge. Before test day, work out roughly how much time you can afford per question, get used to flagging a hard item and coming back to it instead of burning five minutes on one answer, and run at least a couple of full timed sessions in the Prep4away test engine so the clock feels familiar when it counts.
The official blueprint divides the Adobe Workfront Project Manager Certified Professional into 3 domains. The main areas include Intake and Planning (40%), Closeout (10%), Execute (50%). Each domain breaks down into its own subtopics, so scroll up to the complete exam outline above before you plan your study schedule.
6-12 months of Adobe Workfront experience recommended. Certification vendors do adjust these requirements from time to time, so we recommend confirming the current criteria on the official exam page — official AD0-E911 exam information before you register.
The AD0-E911 exam is the official test you need to pass to earn the Adobe Workfront certification at the Professional level. Passing it validates your skills to employers, and for many IT professionals it is a direct step toward better roles and better pay. It also connects to related credentials such as Adobe Workfront Core Developer Professional (AD0-E912), Adobe Workfront Fusion Developer Professional (AD0-E902), Adobe Workfront Core Developer Expert (AD0-E907), so it is worth understanding where this exam sits on your certification path.
The passing score for the AD0-E911 exam is 33 / 50, and the official registration fee is $125 USD. One thing candidates often overlook: if you do not pass, a retake means paying that fee again in full. It is a strong argument for drilling with the 98 practice questions from Prep4away until your mock scores sit comfortably above the bar before you book a seat.
If you take the corresponding AD0-E911 exam within 60 days of purchase and do not pass, you can apply for a full refund under our 100% Money Back Guarantee. Send us a scanned copy of your exam enrollment slip together with your official Score Report PDF within 2 days of taking the exam, and we will process the claim within 7 days. Please note the conditions: sitting the exam within 3 days of purchase does not qualify, the candidate name on the exam record must match the payer's name, and free materials, downloaded-but-never-taken exams, and expired orders are excluded. If you would rather not take a refund, you can exchange your order for two other exam products of equal value at no cost and keep the update service on your original purchase. Delivery itself is instant: the files are available for download right after payment and also reach your mailbox within a minute — contact our customer service team if nothing arrives within 2 hours. There is no limit on how many computers you may install the material on.
Adobe Workfront Project Manager Certified Professional Sample Questions:
A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
- A. Use a customized approval process to route the issue for approval.
- B. Convert the issue into a project using a project template.
- C. Email the management team and request their approval.
Correct Answer: A 🗳️
Explanation: Only visible for Prep4away members. You can sign-up / login (it's free).
Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?
- A. The task duration and planned hours are set to begin on Friday.
- B. The primary task owner has time off logged in Workfront.
- C. The team needs to review the task before confirming the start date.
Correct Answer: A 🗳️
Explanation: Only visible for Prep4away members. You can sign-up / login (it's free).
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
- A. Planned Date
- B. Estimated Date
- C. Projected Date
Correct Answer: C 🗳️
Explanation: Only visible for Prep4away members. You can sign-up / login (it's free).
What is unique to a Scrum iteration?
- A. Workload Balancer for assigning users to tasks
- B. Backlog of stories and issues
- C. Burndown Chart
Correct Answer: C 🗳️
Explanation: Only visible for Prep4away members. You can sign-up / login (it's free).
Which two statements are true about Groups and Teams? (Choose two.)
- A. A Team can be assigned to a task, but a Group cannot be assigned to a task.
- B. Work requests can be routed to either a Group or a Team.
- C. A Group can be assigned to a task, but a Team cannot be assigned to a task.
- D. Objects can be shared with either a Group or a Team.
Correct Answer: A,B 🗳️
Explanation: Only visible for Prep4away members. You can sign-up / login (it's free).
Viewing page 1 out of 20 pages.
Viewing questions 1-5 out of 98 questions.